Officials update public on progression of Bay Park Sewage Treatment Plant after Sandy damage

Officials have given a public update on Bay Park Sewage Treatment Plant following the significant damage it suffered during Sandy.



The county has received more than $800 million in federal funding to upgrade the facility, and today the public received a progress report about how the work is progressing.



Chief Deputy County Executive Rob Walker and the firms overseeing management of the project say that there are currently six active construction projects on the property. They also discussed plans to build a berm to protect the facility in the future, as well as a proposal to build an outflow pipe that would bypass the Reynolds Channel and empty 3 miles south of Long Beach in the Atlantic Ocean.



Legislator Dave Denenberg, the ranking Democrat on the Nassau County Legislature Public Works Committee, says the county and the developers are moving too slowly to upgrade the facility.



"So many of the Sandy-related projects are still in the design phase and construction hasn't gone out to contract, not even out to bid," he says.



The project is scheduled to be completed in four years.


sorry to interrupt
your first 20 are free
Access to News 12 is free for Optimum, Comcast®, Time Warner® and Service ElectricSM customers.
Please enjoy 20 complimentary views of articles, photos, and videos during the next 30 days.
you have reached your 20 view limit
Access to News 12 is free for Optimum, Comcast®, Time Warner® and Service ElectricSM customers.
Please login or create an account to continue enjoying News12.
Our sign-up page is undergoing maintenance and is not currently available. However, you will be given direct access to news12.com while we complete our upgrade.
When we are back up and running you will be prompted at that time to complete your sign in. Until then, enjoy the local news, weather, traffic and more that's "as local as local news gets."